Engelsmann Peters GmbH was commissioned by the City of Kapfenberg to perform the structural analysis for the renovation and expansion of the aging Kapfenberg Ice Arena into the future Kapfenberg City Hall. A central component of the renovation was the restoration of the 54-meter-span, delicate steel roof structure dating from the 1970s. In addition to issues regarding coating and corrosion protection, the most important structural engineering consideration was bringing the structure up to current standards regarding snow and seismic loads. In addition to necessary local node reinforcements, care was taken to carry out the renovation measures with as little impact on the existing structure as possible. This was achieved by reducing dead loads and installing mat collectors to systematically reduce snow loads, thereby enabling the preservation of the existing roof structure. As part of the fundamentally new building services concept designed to meet the building physics requirements of the new hall interior, the planning of the building services and electrical systems in the area of the hall roof was also integrated. In addition to the renovation of the hall’s roof, various other steel structures were implemented as part of the project, such as a utility grating on the roof of the east wing, the renovation of the VIP area, and a steel bridge with a curved floor plan connecting the north and west stands.
The existing reinforced concrete grandstands from the 1970s were also renovated and various local modifications were checked and planned with regard to their impact on the existing structure. In the eastern area, the existing grandstand frames were underpinned in order to accommodate the building services required to operate the ice rink in a new basement room, and the existing building itself was earthquake-proofed. The existing building in the northern area was demolished and replaced by a new concrete building that integrates the new concrete grandstand seating area. A new reinforced concrete building was erected to the south, which will serve as the future dressing rooms. A central element of the project was the construction of the new ice rink, in which around 320 m³ of concrete was poured in a single pour to meet the highest standards of vertical dimensional accuracy.
The circumferential façade from the 1980s was renovated while preserving the existing structure, enabling the installation of insulating glazing to meet the thermal requirements of building physics. Outside the existing façade, a perforated sheet metal façade was attached to the hall roof using a steel substructure, which prevents direct sunlight from reaching the ice rink.
The project was awarded the Austrian Steel Construction Prize 2023 in the "Further use" category.
Further information in the link: Winner of the Austrian Steel Construction Award 2023
client
City of Kapfenberg
Our service
Structural design LP 1-8
architect
.tmp architects
Planning and construction
2019 - 2022
Images